As of Friday May 2017, the Gateway Project Update is as follows:

 

  • The building structure is complete
  • The building is watertight
  • Brickwork at the Eastern end is complete
  • Windows are substantially in place
  • Internal walls are being built
  • Some internal fittings are going in

The next steps are:

 

  • The portico archway is a significant structure. It has commenced
  • The blue glazed bricks on the circular structure on the western end will be laid
  • Rendering will be completed
  • The ramp to the first floor will be added

Now that the weather is sunny we are making good progress. 

 

Dr Paul Burgis
Principal

Also in PLC Sydney Community

issue0817-gateway
Foundation Office at Open Day
Come along and chat to our friendly team, Helen, Susanne and Stephen about the Gateway Legacy Walkway.
Read more
Connections_Extension Centre logo
School Holiday Maths Courses
The PLC Sydney Extension Centre will be running the following Senior Studies Mathematics courses during the forthcoming school holidays...
Read more
issue1416-entrance
Parking Around the College
A reminder to please be considerate of our neighbours when parking near the College.
Read more
issue0817-archives-th
Stories From the Archives
Ex-student, Emmie Russell, founded the NSW Orthoptic Association and co-founded the Orthoptic Association of Australia.
Read more
junior-school-play-ground-ig
Enrolling Your Daughters
Please be aware that places at PLC Sydney are limited. Apply now to save disappointment.
Read more
connections-umat-icon
UMAT Preparation Course
PLC Sydney provides the only school-based UMAT Preparation Course in Australia. Register by Wednesday 7 June 2017.
Read more